Which option is true when working with assumptions?
The correct answer is A. All assumptions should be validated with the customer prior to reaching proposal stage. See the full explanation below for the reasoning.
Question
Which option is true when working with assumptions?
Options
- AAll assumptions should be validated with the customer prior to reaching proposal stage
- BIt is line to use assumptions in your proposal if they are based upon industry standard figures
- COnly the customer's own assumptions should be used within a project proposal
- DAssumptions should be omitted from a project proposal
How the community answered
(17 responses)- A76% (13)
- B6% (1)
- C12% (2)
- D6% (1)