Which factors should be combined to determine the overall risk priority?
The correct answer is D. likelihood and impact. See the full explanation below for the reasoning.
Question
Which factors should be combined to determine the overall risk priority?
Options
- Aimpact and time
- Bimpact and readiness
- Cfrequency and size
- Dlikelihood and impact
How the community answered
(42 responses)- A5% (2)
- B5% (2)
- C14% (6)
- D76% (32)