Which two options are generally part of the process for creating an implementation roadmap? (Choose two )

The correct answer is B. create a detailed bill of materials D. Develop a stakeholder analysis. See the full explanation below for the reasoning.

Question

Which two options are generally part of the process for creating an implementation roadmap? (Choose two )

Options

  • Aconsider inter-dependencies of each building block
  • Bcreate a detailed bill of materials
  • Cbreak down the project into solution building blocks
  • DDevelop a stakeholder analysis

How the community answered

(29 responses)
  • A
    21% (6)
  • B
    72% (21)
  • C
    7% (2)