Which two are parts of an implementation strategy? (Choose two.)

The correct answer is A. Identification of business constraints B. Refinement and validation of dependencies. See the full explanation below for the reasoning.

Question

Which two are parts of an implementation strategy? (Choose two.)

Options

  • AIdentification of business constraints
  • BRefinement and validation of dependencies
  • CTroubleshooting tips for server installation
  • DCriteria for selection of tools to document documenting operating processes
  • EAnalysis of available networking bandwidth

How the community answered

(53 responses)
  • A
    74% (39)
  • C
    17% (9)
  • D
    4% (2)
  • E
    6% (3)