Avaya
78200X · Question #67
There is a recommended order to powering up the IP500 V2: first power up the expansion modules before powering up the control unit. Why is this?
The correct answer is D. All expansion units need to be powered for the control unit to discover them. See the full explanation below for the reasoning.
Question
There is a recommended order to powering up the IP500 V2: first power up the expansion modules before powering up the control unit. Why is this?
Options
- AIt is easier to start with the expansion unit at the top and then work your way down.
- BThe expansion units may not always see the control unit if powered up last.
- CThe expansion units take longer to power up.
- DAll expansion units need to be powered for the control unit to discover them.
How the community answered
(53 responses)- A17% (9)
- B8% (4)
- C4% (2)
- D72% (38)
Community Discussion
No community discussion yet for this question.