Mark works as an Office Assistant for ABC Inc. He uses Microsoft Outlook that has been configured to use an IMAP account. Mark creates a task request, and then he creates an unassigned copy of the…

The correct answer is C. Only one unassigned copy of a task can be created. See the full explanation below for the reasoning.

Question

Mark works as an Office Assistant for ABC Inc. He uses Microsoft Outlook that has been configured to use an IMAP account. Mark creates a task request, and then he creates an unassigned copy of the task. He wants to create another unassigned copy of the task. However, he is not able to create multiple unassigned copies of the task. Which of the following is the cause of the issue?

Options

  • AThe task is a recurring task.
  • BThe task is marked as private.
  • COnly one unassigned copy of a task can be created.
  • DHe has reclaimed the ownership of the task.

How the community answered

(22 responses)
  • B
    9% (2)
  • C
    77% (17)
  • D
    14% (3)