Your customer's network includes three offices and two data centers that are connected by wide area network (WAN) links. Your customer has documented and modeled Lync usage within the current…
The correct answer is B. Perform traffic simu-lation. Networking Guide Network Planning, Monitoring, and Troubleshooting with Lync Server
Produce Lync Network Readiness Documentation
Question
Your customer's network includes three offices and two data centers that are connected by wide area network (WAN) links. Your customer has documented and modeled Lync usage within the current environment. You review the customer's model and confirm that it is accurate. You need to recommend the next step in the Lync network readiness assessment. What should you recommend as the next step?
Options
- AImplement Quality of Service (QoS).
- BPerform traffic simu-lation.
- CCalculate audio capacity for a public switched telephone network (PSTN).
- DCalculate bandwidth estimations over the WAN links.
How the community answered
(53 responses)- A9% (5)
- B83% (44)
- C2% (1)
- D6% (3)
Explanation
Networking Guide Network Planning, Monitoring, and Troubleshooting with Lync Server