During Proof of Concept (POC) testing, the Denver office showed signs of heavy network utilization from Lync intra-site calls causing issues with production network applications. You need to…

The correct answer is A. Quality of Service (QoS). See the full explanation below for the reasoning.

Question

During Proof of Concept (POC) testing, the Denver office showed signs of heavy network utilization from Lync intra-site calls causing issues with production network applications. You need to mitigate the impact of Lync call testing on the network bandwidth during POC testing. Which Lync 2013 feature should you recommend?

Options

  • AQuality of Service (QoS)
  • BLocation Policy
  • CCall Admission Control (CAC)
  • DConferencing Policy

How the community answered

(19 responses)
  • A
    79% (15)
  • B
    11% (2)
  • C
    5% (1)
  • D
    5% (1)