Which of the following activities is the MAIN purpose of the risk assessment process?
The correct answer is D. Calculating the risks to which assets are exposed in their current setting. See the full explanation below for the reasoning.
Question
Which of the following activities is the MAIN purpose of the risk assessment process?
Options
- ACreating an inventory of information assets
- BClassifying and organizing information assets into meaningful groups
- CAssigning value to each information asset
- DCalculating the risks to which assets are exposed in their current setting
How the community answered
(24 responses)- A8% (2)
- B4% (1)
- C4% (1)
- D83% (20)
Community Discussion