712-50 · Question #437
Which of the following are the triple constraints of project management?
The correct answer is C. Scope, time, and cost. management#:~:text=Each%20side%20or%20point%20of,scope%2C%20time%2C%20and%20c
Security Program Management & Operations
Question
Which of the following are the triple constraints of project management?
Options
- ATime, quality, and scope
- BCost, quality, and time
- CScope, time, and cost
- DQuality, scope, and cost
How the community answered
(40 responses)- A5% (2)
- B15% (6)
- C70% (28)
- D10% (4)
Explanation
management#:~:text=Each%20side%20or%20point%20of,scope%2C%20time%2C%20and%20c
Topics
#triple constraints#project management#scope#cost and time