Which of the following are the triple constraints of project management?

The correct answer is C. Scope, time, and cost. management#:~:text=Each%20side%20or%20point%20of,scope%2C%20time%2C%20and%20c

Security Program Management & Operations

Question

Which of the following are the triple constraints of project management?

Options

  • ATime, quality, and scope
  • BCost, quality, and time
  • CScope, time, and cost
  • DQuality, scope, and cost

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    15% (6)
  • C
    70% (28)
  • D
    10% (4)

Explanation

management#:~:text=Each%20side%20or%20point%20of,scope%2C%20time%2C%20and%20c

Topics

#triple constraints#project management#scope#cost and time