712-50 · Question #420

A university recently hired a CISO. One of the first tasks is to develop a continuity of operations plan (COOP). In developing the business impact assessment (BIA), which of the following MOST…

The correct answer is C. Recovery Time Objective (RTO). faqs/#:~:text=The%20recovery%20time%20objective%20(RTO,consequences%20associated%2 0with%20the%20disruption

Security Program Management & Operations

Question

A university recently hired a CISO. One of the first tasks is to develop a continuity of operations plan (COOP). In developing the business impact assessment (BIA), which of the following MOST closely relate to the data backup and restoral?

Options

  • ARecovery Point Objective (RPO)
  • BMean Time to Delivery (MTD)
  • CRecovery Time Objective (RTO)
  • DMaximum Tolerable Downtime (MTD)

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    82% (23)
  • D
    11% (3)

Explanation

faqs/#:~:text=The%20recovery%20time%20objective%20(RTO,consequences%20associated%2 0with%20the%20disruption

Topics

#business impact analysis#RTO#data backup and recovery#continuity planning