A university recently hired a CISO. One of the first tasks is to develop a continuity of operations plan (COOP). In developing the business impact assessment (BIA), which of the following MOST…
The correct answer is C. Recovery Time Objective (RTO). faqs/#:~:text=The%20recovery%20time%20objective%20(RTO,consequences%20associated%2 0with%20the%20disruption
Security Program Management & Operations
Question
A university recently hired a CISO. One of the first tasks is to develop a continuity of operations plan (COOP). In developing the business impact assessment (BIA), which of the following MOST closely relate to the data backup and restoral?
Options
- ARecovery Point Objective (RPO)
- BMean Time to Delivery (MTD)
- CRecovery Time Objective (RTO)
- DMaximum Tolerable Downtime (MTD)
How the community answered
(28 responses)- A4% (1)
- B4% (1)
- C82% (23)
- D11% (3)
Explanation
faqs/#:~:text=The%20recovery%20time%20objective%20(RTO,consequences%20associated%2 0with%20the%20disruption
Topics
#business impact analysis#RTO#data backup and recovery#continuity planning