A security manager has created a risk program. Which of the following is a critical part of ensuring the program is successful?
The correct answer is A. Providing a risk program governance structure. See the full explanation below for the reasoning.
Question
A security manager has created a risk program. Which of the following is a critical part of ensuring the program is successful?
Options
- AProviding a risk program governance structure
- BEnsuring developers include risk control comments in code
- CCreating risk assessment templates based on specific threats
- DAllowing for the acceptance of risk for regulatory compliance requirements
How the community answered
(43 responses)- A79% (34)
- B7% (3)
- C2% (1)
- D12% (5)