Which of the following backup sites takes the longest recovery time?

The correct answer is A. Cold site. A cold site requires the longest recovery time because it provides only the physical space and basic infrastructure (power, network connectivity) - no pre-installed hardware, software, or data exists, meaning everything must be procured, configured, and restored from scratch…

IS Management Controls and Auditing Management

Question

Which of the following backup sites takes the longest recovery time?

Options

  • ACold site
  • BHot site
  • CWarm site
  • DMobile backup site

How the community answered

(30 responses)
  • A
    83% (25)
  • B
    3% (1)
  • C
    3% (1)
  • D
    10% (3)

Explanation

A cold site requires the longest recovery time because it provides only the physical space and basic infrastructure (power, network connectivity) - no pre-installed hardware, software, or data exists, meaning everything must be procured, configured, and restored from scratch before operations can resume. A hot site (B) is wrong because it mirrors the production environment in real time with live systems and data, enabling recovery in hours or even minutes. A warm site (C) falls in between - hardware and software are pre-installed but data must still be restored, giving moderate recovery times (hours to days). A mobile backup site (D) is a portable trailer or van with pre-configured equipment that can be deployed quickly, so recovery is faster than a cold site.

Memory tip: Think of temperature as a proxy for readiness - the colder the site, the longer you wait to "warm it up" before it's usable. Cold = slow, Hot = fast.

Topics

#Disaster recovery#Backup sites#Business continuity#RTO