The correct answer is B. The project was initiated without an effort to get support from impacted business units in the. See the full explanation below for the reasoning.

Question

A newly appointed security officer finds data leakage software licenses that had never been used. The officer decides to implement a project to ensure it gets installed, but the project gets a great deal of resistance across the organization. Which of the following represents the MOST likely reason for this situation?

Options

  • AThe software license expiration is probably out of synchronization with other software licenses
  • BThe project was initiated without an effort to get support from impacted business units in the
  • CThe software is out of date and does not provide for a scalable solution across the enterprise
  • DThe security officer should allow time for the organization to get accustomed to her presence