nerdexam
EC-Council

712-50 · Question #161

Which of the following is considered a project versus a managed process?

The correct answer is D. installation of a new firewall system. See the full explanation below for the reasoning.

Question

Which of the following is considered a project versus a managed process?

Options

  • Amonitoring external and internal environment during incident response
  • Bongoing risk assessments of routine operations
  • Ccontinuous vulnerability assessment and vulnerability repair
  • Dinstallation of a new firewall system

How the community answered

(46 responses)
  • A
    13% (6)
  • B
    7% (3)
  • C
    4% (2)
  • D
    76% (35)

Community Discussion

No community discussion yet for this question.

Full 712-50 Practice