Cisco
700-070 · Question #4
Which step is required during pre-installation of the IX5000?
The correct answer is D. Verify that appropriate licenses, upgrades, and tools are available. See the full explanation below for the reasoning.
Question
Which step is required during pre-installation of the IX5000?
Options
- AHang celling lights.
- BInstall wall panels.
- CVerify that the room floor is level.
- DVerify that appropriate licenses, upgrades, and tools are available.
How the community answered
(27 responses)- A19% (5)
- B4% (1)
- C7% (2)
- D70% (19)
Community Discussion
No community discussion yet for this question.