nerdexam
Microsoft

70-673 · Question #11

Your customer plans to develop a business case for SAM. The customer's SAM Improvement Plan key competency has a Basic maturity level. You need to improve the maturity level to Standardized. What…

The correct answer is C. Obtain budgetary approval for a SAM plan. See the full explanation below for the reasoning.

Question

Your customer plans to develop a business case for SAM. The customer's SAM Improvement Plan key competency has a Basic maturity level. You need to improve the maturity level to Standardized. What should you do?

Options

  • AIdentify a SAM tool.
  • BIdentify roles and staff.
  • CObtain budgetary approval for a SAM plan.
  • DCreate a project plan Gantt chart for a SAM plan.

How the community answered

(52 responses)
  • A
    12% (6)
  • B
    8% (4)
  • C
    77% (40)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.

Full 70-673 Practice