nerdexam
Microsoft

70-576 · Question #143

70-576 Question #143: Real Exam Question with Answer & Explanation

The correct answer is C. Specify the new version number and any upgrade actions required in each of the Feature.xml. See the full explanation below for the reasoning.

Question

In your development environment, you designed new versions of a number of features currently working in a SharePoint 2010 farm. The features are being used throughout the farm at all scope levels. You need to meet the following requirements: - All features on the farm must be upgraded to the newest version. - All existing feature instances must be upgraded to the latest version. - The sites using the features must experience as little downtime as possible. Which approach should you recommend?

Options

  • ADeploy all of the features as one solution package to the farm.
  • BDeploy each of the features in its own solution package to the farm.
  • CSpecify the new version number and any upgrade actions required in each of the Feature.xml
  • DRetract the existing versions of the features.

Community Discussion

No community discussion yet for this question.

Full 70-576 Practice