In your development environment, you designed new versions of a number of features currently working in a SharePoint 2010 farm. The features are being used throughout the farm at all scope levels…

The correct answer is C. Specify the new version number and any upgrade actions required in each of the Feature.xml. See the full explanation below for the reasoning.

Question

In your development environment, you designed new versions of a number of features currently working in a SharePoint 2010 farm. The features are being used throughout the farm at all scope levels. You need to meet the following requirements:

  • All features on the farm must be upgraded to the newest version.
  • All existing feature instances must be upgraded to the latest

version.

  • The sites using the features must experience as little downtime as

possible. Which approach should you recommend?

Options

  • ADeploy all of the features as one solution package to the farm.
  • BDeploy each of the features in its own solution package to the farm.
  • CSpecify the new version number and any upgrade actions required in each of the Feature.xml
  • DRetract the existing versions of the features.

How the community answered

(41 responses)
  • A
    17% (7)
  • B
    5% (2)
  • C
    71% (29)
  • D
    7% (3)

Community Discussion

No community discussion yet for this question.