You are planning an upgrade to a SharePoint 2010 application. You have the following requirements: - Modify an existing workflow to include a new code activity. - Ensure running instances of the…

The correct answer is D. Incrementing the version of the workflow assembly, deploying to the GAC, and modifying the. See the full explanation below for the reasoning.

Question

You are planning an upgrade to a SharePoint 2010 application. You have the following requirements:

  • Modify an existing workflow to include a new code activity.
  • Ensure running instances of the workflow continue to work.
  • Ensure new instances of the workflow include the modifications.

You need to plan the upgrade the application to meet these requirements. After the workflow code is modified, what should your plan specify?

Options

  • ADeploying the code to the global assembly cache (GAC) and deactivating the workflow
  • BIncrementing the version of the workflow assembly, deploying to the GAC, and activating
  • CIncrementing the version of the workflow assembly, deploying to the GAC, deactivating the
  • DIncrementing the version of the workflow assembly, deploying to the GAC, and modifying the

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    12% (3)
  • C
    8% (2)
  • D
    76% (19)