You create a timer job. You need to debug the timer job. To which process should you attach the debugger?
The correct answer is B. owstimer.exe. MNEMONIC RULE: "timer job = owstimer.exe" How to: Debug a Timer Job
Developing Business Logic
Question
You create a timer job. You need to debug the timer job. To which process should you attach the debugger?
Options
- Adevenv.exe
- Bowstimer.exe
- Cspucworkerprocess.exe
- Dw3wp.exe
How the community answered
(36 responses)- A11% (4)
- B81% (29)
- C6% (2)
- D3% (1)
Explanation
MNEMONIC RULE: "timer job = owstimer.exe" How to: Debug a Timer Job