Question
Your development team uses Scrum as its process framework. You are attempting to increase efficiency, code quality, and limit scope creep by making some changes to your team's development process. You need to identify key metrics for measuring the effect of any changes to your process. Which three key metrics should you use? Each correct answer presents part of the solution.
Options
- Anumber of story points delivered during the sprint
- Bnumber of manual test cases created
- Cnumber of bugs reported by testers
- Dnumber of tasks added to the sprint after the sprint starts
- Enumber of classes in the code-base
- Fnumber of items added to the product backlog