nerdexam
Microsoft

70-499 · Question #76

70-499 Question #76: Real Exam Question with Answer & Explanation

The correct answer is C. Analyze items in the product backlog for the next sprint.. See the full explanation below for the reasoning.

Question

You are using the Microsoft Visual Studio Scrum 2.0 process template. You recently finished a sprint. You need to conduct a retrospective meeting prior to planning the next sprint. What should you do?

Options

  • AAnalyze and revise the story points of the work items completed in the previous sprint.
  • BAnalyze the previous sprint to identify what the team is going to do differently during the
  • CAnalyze items in the product backlog for the next sprint.
  • DDetermine which items have been finished on the previous sprint.

Community Discussion

No community discussion yet for this question.

Full 70-499 Practice