You are using the Microsoft Solution Framework (MSF) for Capability Maturity Model Integration (CMMI) Process Improvement 6.0 process template. A stakeholder has requested a change, but the change…

The correct answer is D. Create another change request work item. If a change request does not receive the attention that it requires, escalate the matter by creating an issue work item. Link the new issue to the change request, and escalate the issue to get the change request impact assessment on track.

Manage application lifecycle

Question

You are using the Microsoft Solution Framework (MSF) for Capability Maturity Model Integration (CMMI) Process Improvement 6.0 process template. A stakeholder has requested a change, but the change request has not received the attention that it requires. You need to escalate the change request. What should you do?

Options

  • ACreate an impediment work item.
  • BCreate a bug work item.
  • CCreate an issue work item.
  • DCreate another change request work item.

How the community answered

(41 responses)
  • A
    2% (1)
  • B
    12% (5)
  • C
    10% (4)
  • D
    76% (31)

Explanation

If a change request does not receive the attention that it requires, escalate the matter by creating an issue work item. Link the new issue to the change request, and escalate the issue to get the change request impact assessment on track.

Topics

#MSF CMMI#change request#work item escalation#process template