70-499 · Question #71

You manage a project for which the team has not delivered all of the story points committed to in a previous sprint. You want to define the amount of work the team can commit to for the next sprint…

The correct answer is B. Review the team velocity to define the amount of work. See the full explanation below for the reasoning.

Question

You manage a project for which the team has not delivered all of the story points committed to in a previous sprint. You want to define the amount of work the team can commit to for the next sprint of the project. What should you do?

Options

  • AReview the sprint burndown to define the amount of work.
  • BReview the team velocity to define the amount of work
  • CAllow the product owner to define the amount of work.
  • DReview capacity of the team to define the amount of work.

How the community answered

(16 responses)
  • A
    6% (1)
  • B
    75% (12)
  • C
    6% (1)
  • D
    13% (2)