Question

You manage a project for which the team has not delivered all of the story points committed to in a previous sprint. You want to define the amount of work the team can commit to for the next sprint of the project. What should you do?

Options

  • AReview the sprint burndown to define the amount of work.
  • BReview the team velocity to define the amount of work
  • CAllow the product owner to define the amount of work.
  • DReview capacity of the team to define the amount of work.