You are developing a release plan for a new project. You need to create a risk management plan. Which three activities or elements should you include in your plan? (Each correct answer presents a…

The correct answer is A. Probability assessment C. Resolution planning D. Impact analysis. See the full explanation below for the reasoning.

Question

You are developing a release plan for a new project. You need to create a risk management plan. Which three activities or elements should you include in your plan? (Each correct answer presents a complete solution. Choose three.)

Options

  • AProbability assessment
  • BAssumptions
  • CResolution planning
  • DImpact analysis
  • EResource planning
  • FConstraints

How the community answered

(72 responses)
  • A
    85% (61)
  • B
    4% (3)
  • E
    8% (6)
  • F
    3% (2)

Community Discussion

No community discussion yet for this question.