70-499 · Question #48
You are utilizing the Microsoft Visual Studio Scrum 2.0 process template. You lead a development team that includes business analysts, developers, and testers. You need to capture requirements and…
The correct answer is C. Add product backlog item (PBI) work items. In Team Foundation Server, the Product Backlog Item (PBI) work item type enables the Scrum Team to capture all of these various requirements with as little documentation as possible. In fact, only the title field is required. Later, as more detail emerges, the PBI can be…
Question
Options
- ACreate a document that details the requirements and acceptance tests.
- BCreate a document that details the requirements and acceptance tests.
- CAdd product backlog item (PBI) work items.
- DCreate a spreadsheet that details the requirements and acceptance tests.
How the community answered
(22 responses)- A5% (1)
- B5% (1)
- C82% (18)
- D9% (2)
Explanation
In Team Foundation Server, the Product Backlog Item (PBI) work item type enables the Scrum Team to capture all of these various requirements with as little documentation as possible. In fact, only the title field is required. Later, as more detail emerges, the PBI can be updated to include business value, acceptance criteria, and the Development Team's latest estimation of Professional Scrum Development with Microsoft Visual Studio 2012 p. 67
Topics
Community Discussion
No community discussion yet for this question.