70-499 · Question #44
70-499 Question #44: Real Exam Question with Answer & Explanation
Sign in or unlock 70-499 to reveal the answer and full explanation for question #44. The question stem and answer options stay visible for context.
Question
You manage a development team that has been assigned the task of developing a reporting application. The team holds a kickoff meeting with the stakeholders to document user requirements. You review the draft requirements list that results from this meeting. You need to indicate which requirements likely will require rework before you can send the requirements list to the development team. Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
Options
- AIdentify requirements that are independent of other requirements.
- BIdentify requirements that cannot be tested easily.
- CIdentify requirements that do not have estimates.
- DIdentify requirements that depend on other requirements.
- EIdentify requirements that provide little business value.