nerdexam
Microsoft

70-499 · Question #38

You manage a project that has three teams working in parallel on a single codebase using a Scrum process methodology. You need to ensure that each team can manage work separately while editing a…

The correct answer is C. Within a single team project, create three teams. See the full explanation below for the reasoning.

Question

You manage a project that has three teams working in parallel on a single codebase using a Scrum process methodology. You need to ensure that each team can manage work separately while editing a shared code base. What should you do?

Options

  • AWithin a single team project, create separate iteration paths for each team.
  • BCreate a team project for each team, assigning different team members to each team project.
  • CWithin a single team project, create three teams.
  • DCreate a team project for each team, assigning all team members to each team project.

How the community answered

(47 responses)
  • A
    2% (1)
  • B
    9% (4)
  • C
    74% (35)
  • D
    15% (7)

Community Discussion

No community discussion yet for this question.

Full 70-499 Practice