nerdexam
Microsoft

70-499 · Question #2

You are the product owner for a new application. You have the list of product backlog items (PBIs) with assigned business values for the first release of the application. You will be working with an…

The correct answer is B. Ask the development team to provide high level estimates to complete each PBI. C. Assign the PBIs to different sprints to define the release. E. Schedule the release using the Iteration Planning workbook. Not clear because according to Planning a release they say: Note Release planning is no longer an official event in Scrum. It's assumed that every organization will do some level of release planning. As far as Scrum is concerned, keeping the Product Backlog healthy and…

Design and implement a release management strategy

Question

You are the product owner for a new application. You have the list of product backlog items (PBIs) with assigned business values for the first release of the application. You will be working with an established scrum master and development team. You know the team's capacity and the planned sprint duration. You need to plan the release schedule based on your existing backlog. Which three actions should you and the team perform? (Each correct answer presents part of the solution. Choose three.)

Options

  • AAsk the development team to decompose the PBIs into individual tasks and estimate hours.
  • BAsk the development team to provide high level estimates to complete each PBI.
  • CAssign the PBIs to different sprints to define the release.
  • DUse the TFS 2012 task board features.
  • ESchedule the release using the Iteration Planning workbook.
  • FOrder the product backlog by business value.

How the community answered

(59 responses)
  • A
    3% (2)
  • B
    76% (45)
  • D
    14% (8)
  • F
    7% (4)

Explanation

Not clear because according to Planning a release they say: Note Release planning is no longer an official event in Scrum. It's assumed that every organization will do some level of release planning. As far as Scrum is concerned, keeping the Product Backlog healthy and estimated is the best input for accurate release planning. Professional Scrum Development with Microsoft Visual Studio 2012 p.160

Topics

#release planning#product backlog#sprint estimation#Iteration Planning workbook

Community Discussion

No community discussion yet for this question.

Full 70-499 Practice