You are using the Microsoft Framework (MSF) for Capability Maturity Model Integration (CMMI) Process Improvement 6.0 process template. You are the scrum master. You need to assign product…

The correct answer is B. Find the dependencies among the product requirements. C. Prioritize each of the requirements. E. Estimate the cost of each of the requirements. See the full explanation below for the reasoning.

Question

You are using the Microsoft Framework (MSF) for Capability Maturity Model Integration (CMMI) Process Improvement 6.0 process template. You are the scrum master. You need to assign product requirements to an iteration. Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

Options

  • ACreate a test harness to confirm that the business requirements are understood.
  • BFind the dependencies among the product requirements.
  • CPrioritize each of the requirements.
  • DCreate a prototype to validate whether or not the requirement can be accomplished.
  • EEstimate the cost of each of the requirements.

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    77% (27)
  • D
    17% (6)