70-458 · Question #104

You are a database administrator for a Microsoft SQL Server 2012 instance. You need to ensure that data can be migrated from a production server to two reporting servers with minimal data latency…

The correct answer is C. Availability Groups. See the full explanation below for the reasoning.

Question

You are a database administrator for a Microsoft SQL Server 2012 instance. You need to ensure that data can be migrated from a production server to two reporting servers with minimal data latency. You also need to ensure that data on the reporting server is always accessible. Which solution should you use?

Options

  • AChange Data Capture
  • BDatabase snapshot
  • CAvailability Groups
  • DLog Shipping

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    17% (5)
  • C
    70% (21)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.

Full 70-458 Practice