You administer a SQL Server 2008 infrastructure. A SQL Server instance contains a transactional database. You design a plan to back up and restore a database. The current transactional database…

The correct answer is A. Restore the differential backups from Monday. C. Restore log backups from Monday 02:15 hr to 15:15 hr by using the STANDBY option. D. Restore the full back up from Saturday. See the full explanation below for the reasoning.

Question

You administer a SQL Server 2008 infrastructure. A SQL Server instance contains a transactional database. You design a plan to back up and restore a database. The current transactional database backup strategy has the following features:

You simulate a complete hardware failure at 15:29 hr on Monday. The test includes inconsistent application data beginning at 15:00 hr. You need to ensure that you can restore the database up You need to ensure that the backup jobs have a minimal effect on the performance of the server to 15:00 hr on Monday. Which three steps should you perform? (Each correct answer presents part of the solution. Choose three.)

Options

  • ARestore the differential backups from Monday.
  • BRestore the differential backups from Sunday.
  • CRestore log backups from Monday 02:15 hr to 15:15 hr by using the STANDBY option.
  • DRestore the full back up from Saturday.
  • ERestore log backups from Monday 02:15 hr to 15:15 hr by using the STOPAT Option.

How the community answered

(54 responses)
  • A
    80% (43)
  • B
    15% (8)
  • E
    6% (3)