You create a SQL Server 2008 Analysis Services (SSAS) solution. Your solution has a date dimension named Date along with a hierarchy named Calendar. The Calendar hierarchy has levels for the Year…

The correct answer is A. PeriodsToDate([DimTime].[Yr-Qtr-Mth].[Year], [DimTime].[Yr-Qtr-Mth].[Month].[July 2007]). See the full explanation below for the reasoning.

Question

You create a SQL Server 2008 Analysis Services (SSAS) solution. Your solution has a date dimension named Date along with a hierarchy named Calendar. The Calendar hierarchy has levels for the Year, Quarter, Month, and Date attributes. You need to create a named set that refers to the first seven months of the year 2007. Which expression should you write for the named set?

Options

  • APeriodsToDate([DimTime].[Yr-Qtr-Mth].[Year], [DimTime].[Yr-Qtr-Mth].[Month].[July 2007])
  • BPeriodsToDate([DimTime].[Yr-Qtr-Mth].[Month], [DimTime].[Yr-Qtr-Mth].[Month].[July 2007])
  • CParallelPeriod([DimTime].[Yr-Qtr-Mth].[Year], 7, [DimTime].[Yr-Qtr-Mth].[Month].[July 2007])
  • DParallelPeriod ([DimTime].[Yr-Qtr-Mth].[Month], 7, [DimTime].[Yr-Qtr-Mth].[Month].[July 2007])

How the community answered

(27 responses)
  • A
    74% (20)
  • B
    7% (2)
  • C
    4% (1)
  • D
    15% (4)