Question
You work as a Project Manager for Tech Perfect Inc. Several projects are running under your supervision. Martha, a team leader of a project, informs you about the performance indexes of her project. The schedule performance index (SPI) of her project is 0.835. What does this figure indicate?
Options
- AThe schedule performance is better than expected.
- BThe schedule performance is below expectation.
- CThe cost performance is better than expected.
- DThe schedule performance is right on target.