You work as a Project Administrator for company.com Inc. One of your team members, Ralph, reports that he is trying to customize, through his Microsoft Project Professional, the Gantt Chart view but…

The correct answer is D. Ralph cannot rename the Gantt Chart, as it is an Enterprise Global default view. Ralph cannot rename the Gantt Chart, because no one can rename or delete an Enterprise Global default view. The most common default views are Gantt Chart, Detailed Gantt Chart, Calendar, and the Network Diagram. Answer option A is incorrect. This is not enough information to be…

Configuring Project Server 2010

Question

You work as a Project Administrator for company.com Inc. One of your team members, Ralph, reports that he is trying to customize, through his Microsoft Project Professional, the Gantt Chart view but he receives an error when he tries to rename the view. What is the most likely problem in this scenario?

Options

  • ARalph cannot rename the Gantt Chart.
  • BRalph cannot rename the Gantt Chart, as it is an EPM Global view used by all Microsoft Project
  • CRalph cannot rename the Gantt Chart, as it is a project view.
  • DRalph cannot rename the Gantt Chart, as it is an Enterprise Global default view.

How the community answered

(52 responses)
  • A
    2% (1)
  • B
    12% (6)
  • C
    8% (4)
  • D
    79% (41)

Explanation

Ralph cannot rename the Gantt Chart, because no one can rename or delete an Enterprise Global default view. The most common default views are Gantt Chart, Detailed Gantt Chart, Calendar, and the Network Diagram. Answer option A is incorrect. This is not enough information to be considered correct. Answer option C is incorrect. This is not a valid reason for why Ralph cannot delete the Gantt Chart. Answer option B is incorrect. There is not a category of views called an EPM Global view, so this choice is wrong. What is a Gantt chart? A Gantt chart is a type of bar chart that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown structure of the project. Some Gantt charts also show the dependency (i.e, precedence network) relationships between activities. Gantt charts have become a common technique for representing the phases and activities of a project work breakdown structure (WBS), so they can be understood by a wide audience.