You administer a Forefront Identity Management (FIM) 2010 server in your company network. You have two managers named User1 and User2. You need to configure the approval activity for a new workflow…
The correct answer is B. Create two separate activities. To fulfill the requirements of independent and sequential approvals for User1 and User2, the workflow must be configured with two distinct approval activities.
Question
Options
- ACreate two separate activities.
- BCreate two separate activities.
- CCreate a single activity.
- DCreate a single activity.
How the community answered
(23 responses)- A13% (3)
- B78% (18)
- C4% (1)
- D4% (1)
Why each option
To fulfill the requirements of independent and sequential approvals for User1 and User2, the workflow must be configured with two distinct approval activities.
While choice A presents the same textual option, B is designated as the correct answer for fulfilling the specified workflow requirements.
Creating two separate approval activities allows each manager to receive and act on their own request independently. These activities can then be linked sequentially within the workflow, ensuring that User2's approval step is initiated only after User1 has completed their approval, thereby satisfying both independent and sequential processing requirements.
Creating a single activity would not allow for independent approvals by User1 and User2, nor would it inherently support the required sequential processing where User2's approval only starts after User1's completion.
Creating a single activity would not allow for independent approvals by User1 and User2, nor would it inherently support the required sequential processing where User2's approval only starts after User1's completion.
Concept tested: FIM Workflow Sequential Approval Configuration