Which three tasks should be completed no later than 15 minutes before the scheduled start time of a virtual session? (Choose three)
The correct answer is A. Conduct a brief needs assessment. E. Start the session. G. Assign participantsprivileges. See the full explanation below for the reasoning.
Question
Which three tasks should be completed no later than 15 minutes before the scheduled start time of a virtual session? (Choose three)
Options
- AConduct a brief needs assessment.
- BUploads presentation files or materials.
- CDevelop effective session materials.
- DConsider how learning will be measured.
- EStart the session.
- FMake sure your computer has the most up-to-date software versions.
- GAssign participantsprivileges.