A technician has completed the installation of an Avaya ACETM on Linux High Availability (HA) configuration. While performing the final verification, it is discovered that a failover has occurred to…

The correct answer is D. Review log files from the Avaya ACETM GUI (Fault-Logs Download). See the full explanation below for the reasoning.

Question

A technician has completed the installation of an Avaya ACETM on Linux High Availability (HA) configuration. While performing the final verification, it is discovered that a failover has occurred to the Standby server. To determine what caused the failover, where can more detailed information be obtained?

Options

  • AReview performance metrics online using the Avaya ACETM GUI (Performance - System Metrics).
  • BReview the troubleshooting documents from the Avaya ACETM GUI (Help - Product
  • CReview query active alarms using Linux commands.
  • DReview log files from the Avaya ACETM GUI (Fault-Logs Download).

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    9% (2)
  • C
    4% (1)
  • D
    83% (19)