Which three pieces of information must be maintained for all stakeholders as part of the change management process? (Choose three.)

The correct answer is B. the date and time that the change was applied and on which device C. the original change request form that indicates why the change is necessary E. a description of the actual change itself (configuration, program code, and so on). See the full explanation below for the reasoning.

Question

Which three pieces of information must be maintained for all stakeholders as part of the change management process? (Choose three.)

Options

  • Athe location of the person who applied the change
  • Bthe date and time that the change was applied and on which device
  • Cthe original change request form that indicates why the change is necessary
  • Dthe size of the change (in bytes)
  • Ea description of the actual change itself (configuration, program code, and so on)
  • Fthe names of the current members of the change advisory board
  • Gthe industrial protocol that is used

How the community answered

(42 responses)
  • A
    2% (1)
  • B
    76% (32)
  • D
    12% (5)
  • F
    7% (3)
  • G
    2% (1)