An administrator created a default policy for the company. Additionally, separate policies for the production environment and the test and development environment were created, based on the company…

The correct answer is D. Objects assigned to the Production policy will be affected. D is correct because policies in this type of management platform (e.g., VMware vRealize Operations) are scoped individually - disabling metrics in the Production policy only affects the virtual machines assigned to that policy. The Production and TestDev policies are siblings…

Deploying and Configuring vRealize Operations

Question

An administrator created a default policy for the company. Additionally, separate policies for the production environment and the test and development environment were created, based on the company policy. Refer to the exhibit:

What will be the impact, if any, of disabling some virtual machine metrics in the Production policy?

Exhibit

5V0-35.21 question #65 exhibit

Options

  • AObjects assigned to the Production and TestDev policies will be affected.
  • BAll objects will be affected because disabling metrics in a policy will disable them globally.
  • CThere will be no impact because metrics cannot be disabled in policies.
  • DObjects assigned to the Production policy will be affected.

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    9% (2)
  • C
    9% (2)
  • D
    78% (18)

Explanation

D is correct because policies in this type of management platform (e.g., VMware vRealize Operations) are scoped individually - disabling metrics in the Production policy only affects the virtual machines assigned to that policy. The Production and TestDev policies are siblings derived from the company default, not parent-child of each other, so changes to one do not propagate to the other.

Why the distractors fail:

  • A is wrong because TestDev is a separate sibling policy; modifying Production has no effect on objects assigned to TestDev.
  • B is wrong because policy changes are never global by default - they are scoped to the policy where the change is made.
  • C is wrong because metrics absolutely can be disabled within a policy; that's a core feature of policy customization.

Memory tip: Think of policies like sibling employees who each got a copy of the company handbook. If one sibling annotates their copy, only their behavior changes - the other sibling's copy is untouched.