VCF design workshops have been conducted, and the architect collected the following customer requirements for the newly planned VCF infrastructure: - The new VCF infrastructure is targeting two…
The correct answer is A. 12-hosts workload domain for both zones, having an 8-hosts DEV/UAT cluster, and a 4-hosts. See the full explanation below for the reasoning.
Question
VCF design workshops have been conducted, and the architect collected the following customer requirements for the newly planned VCF infrastructure:
- The new VCF infrastructure is targeting two zones: DEV/UAT and DMZ.
- The infrastructure team requested that the number of management components be minimized
as much as possible.
- Eight hosts should be ordered for the DEV/UAT environment.
- Four hosts should be ordered for the DMZ environment.
- The DEV/UAT workloads must comply with an erasure coding vSAN storage policy and have
the ability to tolerate the failure of two hosts. Which workload domain sizing will be required to achieve these requirements?
Options
- A12-hosts workload domain for both zones, having an 8-hosts DEV/UAT cluster, and a 4-hosts
- B8-hosts DEV/UAT workload domain, having an 8-hosts DEV/UAT cluster, and a 4-hosts DMZ
- C8-hosts DEV/UAT workload domain, having a 4-hosts DEV cluster, and a 4-hosts UAT cluster, in
- D12-hosts workload domain for both zones, having a 4-hosts DEV cluster, a 4-hosts UAT cluster,
How the community answered
(28 responses)- A71% (20)
- B11% (3)
- C14% (4)
- D4% (1)