nerdexam
Broadcom-VMware

5V0-22.23 · Question #68

Due to a planned power outage, an administrator decides to shut down the vSAN cluster using the Shutdown Cluster Wizard. The administrator starts by checking the vSAN health service to confirm the…

The correct answer is C. Turn off High Availability. https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vsan- monitoring.doc/GUID-31B4F958-30A9-4BEC-819E-32A18A685688.html

Administering and Operating VMware vSAN

Question

Due to a planned power outage, an administrator decides to shut down the vSAN cluster using the Shutdown Cluster Wizard. The administrator starts by checking the vSAN health service to confirm the cluster is healthy and then powers off all virtual machines (VMs) including vCLS VMs. Which step needs to be taken before starting the Shutdown Cluster Wizard?

Options

  • APlace all ESXi hosts into maintenance mode
  • BDisable cluster member updates from vCenter Server
  • CTurn off High Availability
  • DShutdown vCenter

How the community answered

(39 responses)
  • A
    3% (1)
  • C
    92% (36)
  • D
    5% (2)

Explanation

https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vsan- monitoring.doc/GUID-31B4F958-30A9-4BEC-819E-32A18A685688.html

Topics

#cluster shutdown#High Availability#Shutdown Cluster Wizard#maintenance

Community Discussion

No community discussion yet for this question.

Full 5V0-22.23 Practice