Due to a planned power outage, an administrator decides to shut down the vSAN cluster using the Shutdown Cluster Wizard. The administrator starts by checking the vSAN health service to confirm the…
The correct answer is C. Turn off High Availability. https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vsan- monitoring.doc/GUID-31B4F958-30A9-4BEC-819E-32A18A685688.html
Administering and Operating VMware vSAN
Question
Due to a planned power outage, an administrator decides to shut down the vSAN cluster using the Shutdown Cluster Wizard. The administrator starts by checking the vSAN health service to confirm the cluster is healthy and then powers off all virtual machines (VMs) including vCLS VMs. Which step needs to be taken before starting the Shutdown Cluster Wizard?
Options
- APlace all ESXi hosts into maintenance mode
- BDisable cluster member updates from vCenter Server
- CTurn off High Availability
- DShutdown vCenter
How the community answered
(39 responses)- A3% (1)
- C92% (36)
- D5% (2)
Explanation
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vsan- monitoring.doc/GUID-31B4F958-30A9-4BEC-819E-32A18A685688.html
Topics