multiple data centers, the customer relayed the following information: Highest possible mitigation during a host failure in terms of capacity. A constraint in this year's IT budget. What should the…

The correct answer is B. Enable host build reserve. Performance services and IOinsight Metrics used for performance analysis. Operation reserve for internal VSAN operations. https://blogs.vmware.com/virtualblocks/2020/09/24/effective-capacity-management-with-vsan-7-

Planning and Design VMware HCI Implementations

Question

multiple data centers, the customer relayed the following information:

  • Highest possible mitigation during a host failure in terms of capacity.
  • A constraint in this year's IT budget.

What should the architect recommend?

Options

  • AEnable operations reserve.
  • BEnable host build reserve.
  • CEnable performance services.
  • DEnable IOInsight Metrics.

How the community answered

(55 responses)
  • A
    5% (3)
  • B
    78% (43)
  • C
    4% (2)
  • D
    13% (7)

Explanation

Performance services and IOinsight Metrics used for performance analysis. Operation reserve for internal VSAN operations. https://blogs.vmware.com/virtualblocks/2020/09/24/effective-capacity-management-with-vsan-7-

Topics

#host build reserve#capacity planning#host failure mitigation#budget constraint