The clomd service has stopped on 1 host in a 3 node vSAN cluster. All other services on the host, as well as the other 2, are healthy. Additionally, the unmodified vSAN Default Storage Policy is in…

The correct answer is A. VM deployment will fail. See the full explanation below for the reasoning.

Question

The clomd service has stopped on 1 host in a 3 node vSAN cluster. All other services on the host, as well as the other 2, are healthy. Additionally, the unmodified vSAN Default Storage Policy is in use. Which would be an expected outcome for a new VM deployed into the vSAN cluster?

Options

  • AVM deployment will fail.
  • BVM deployment will complete but VM 10 will fail.
  • CVM deployment will complete but performance will be degraded.
  • DVM deployment will be deferred by vCenter.

How the community answered

(26 responses)
  • A
    81% (21)
  • B
    12% (3)
  • C
    4% (1)
  • D
    4% (1)