During the course of a risk analysis your IT auditor identified threats and potential impacts. Next, your IT auditor should:
The correct answer is A. Identify and evaluate the existing controls. See the full explanation below for the reasoning.
Question
During the course of a risk analysis your IT auditor identified threats and potential impacts. Next, your IT auditor should:
Options
- AIdentify and evaluate the existing controls.
- BDisclose the threats and impacts to management.
- CIdentify information assets and the underlying systems.
- DIdentify and assess the risk assessment process used by management.
How the community answered
(25 responses)- A76% (19)
- B12% (3)
- C4% (1)
- D8% (2)