One of the MAIN goals of a Business Continuity Plan is to
The correct answer is C. Provide step by step plans to recover business processes in the event of a disaster. See the full explanation below for the reasoning.
Question
One of the MAIN goals of a Business Continuity Plan is to
Options
- AEnsure all infrastructure and applications are available in the event of a disaster
- BAllow all technical first-responders to understand their roles in the event of a disaster
- CProvide step by step plans to recover business processes in the event of a disaster
- DAssign responsibilities to the technical teams responsible for the recovery of all data.
How the community answered
(38 responses)- A8% (3)
- B16% (6)
- C74% (28)
- D3% (1)