When project costs continually increase throughout implementation due to large or rapid changes in customer or user requirements, this is commonly known as:

The correct answer is B. Scope creep. See the full explanation below for the reasoning.

Question

When project costs continually increase throughout implementation due to large or rapid changes in customer or user requirements, this is commonly known as:

Options

  • ACost/benefit adjustments
  • BScope creep
  • CPrototype issues
  • DExpectations management

How the community answered

(31 responses)
  • A
    13% (4)
  • B
    77% (24)
  • C
    3% (1)
  • D
    6% (2)