Which of the following are the triple constraints of project management?

The correct answer is C. Scope, time, and cost. See the full explanation below for the reasoning.

Question

Which of the following are the triple constraints of project management?

Options

  • ATime, quality, and scope
  • BCost, quality, and time
  • CScope, time, and cost
  • DQuality, scope, and cost

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    9% (3)
  • C
    85% (28)
  • D
    3% (1)