Which of the following is the BEST indicator of a successful project?

The correct answer is D. the deliverables are accepted by the key stakeholders. See the full explanation below for the reasoning.

Question

Which of the following is the BEST indicator of a successful project?

Options

  • Ait is completed on time or early as compared to the baseline project plan
  • Bit meets most of the specifications as outlined in the approved project definition
  • Cit comes in at or below the expenditures planned for in the baseline budget
  • Dthe deliverables are accepted by the key stakeholders

How the community answered

(32 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    9% (3)
  • D
    81% (26)