512-50 · Question #162

When managing the critical path of an IT security project, which of the following is MOST important?

The correct answer is D. Knowing the milestones and timelines of deliverables. See the full explanation below for the reasoning.

Question

When managing the critical path of an IT security project, which of the following is MOST important?

Options

  • AKnowing who all the stakeholders are.
  • BKnowing the people on the data center team.
  • CKnowing the threats to the organization.
  • DKnowing the milestones and timelines of deliverables.

How the community answered

(52 responses)
  • A
    8% (4)
  • B
    17% (9)
  • C
    4% (2)
  • D
    71% (37)

Community Discussion

No community discussion yet for this question.